ROOF TILE PROGRESS


ROOF TILE PROGRESS


WALL FINISHING


ROOF TILES PROGRESS


FINAL PLASTERING PROGRESS




普爱学园四恩楼建筑工程墙面工程已经接近70%完成。接下来即将开始屋瓦以及砌红砖工程。四恩楼琉璃瓦片预算下星期将抵达槟城,来自中国的工作人员将抵达槟城进行安装琉璃瓦工程。依据中国工人经验所言,这项安装工程将耗时2个月完成。 至今,普爱学园一共筹获马币45,000令吉,这是来自900位大众所乐捐的琉璃瓦款项. 四恩楼建筑工程进度如下:1. 电线安装接近50%完成。2. 砌砖工程接近95%完成。3. 墙面工程接近70%完成。 在此,呼吁大众继续支持普爱学园四恩楼建筑工程,以便四恩楼早日竣工落成。

Press release on 25th August 2010, Wednesday The building progress for wall plastering was almost 70% completed. We are now starting on the root tiles process with attach with red brick. The Liu Li Roof Tiles was shipped from China will going to arrive next week for the Chinese worker to complete the tiles project. According to the worker, the tiles job will taking almost 2 months for the final completion. For time being, we are only received RM45K from 900 tiles donors (each tile is RM50/set). We are still looking around 2400 tiles donors to complete the roof project. The another progress still going at the site is stated as below 1. Electrical Wire installation almost 50% have completed.2. Brick construction almost 95% have completed.3. Wall plastering almost 70% have completed. Looking Foward from your support.

RegardsCK

2010年8月6日星期五

BLOOD DONATION